Safe Job Procedures

SJP-009 Light Fixture Installation

Hazards

PPE Required

Additional Requirements (if any)

Working at height

Hazardous Electrical Energy

Slips and Trips

Exposed Nails

Heavy Loads

Hard hat

Gloves

Safety Glasses

Protective Footwear

Hi-vis clothing

Hand tool, electrical power tools, portable ladder.

Light Fixtures.

Safe Work Practices
  • All work to be performed by a competent worker as defined in the occupational health and safety code.
  • Supervisor to be trained in risk identification, assessment and control..
  • All personnel to maintain a tidy work area on site at all times. PPE is to be worn at all times on site.
  • Hand tools and ladders to be checked regularly.
  • Supervisor to be appropriately trained, qualified and competent in OHS and electrical practices for the task.
  • Supervisor to carry out daily inspections of work site for hazards.
  • Ensure you are familiar with the Electrical SJP before starting work.
Safe Job Procedure
  1. Confirm layout and make sure area is clear.
  2. Gather material. Make sure you have what you need and implement manual handling SJP.
  3. Make sure you have the right wiring and test before starting work.
  4. Begin installation from ladder or aerial lift platform install fixtures and terminate wiring. Follow SJP for portable ladders.
  5. After completing the installation, ensure the fixture is secured and installed to the relevant specification.